Management and Cost Accounting, 10th Edition Solution Manual
Preview Extract
Cost assignment
Solutions to Chapter 3 questions
(a) For the answer to this question see โBudgeted overhead ratesโ in Chapter 3.
(b) A lower production overhead rate does not necessarily indicate that factory X is
more efficient than factory Y. The reasons for this are:
(i) Factory Yโs operations might be highly mechanized, resulting in large
depreciation costs, whereas factory Xโs operations might be labour-intensive.
Consequently products produced in factory Y will incur higher overhead and
lower labour costs, whereas products produced in factory X will incur lower
overhead and higher labour costs.
(ii) Factory Y may have invested in plant with a larger operating capacity in
order to meet future output. This will result in larger fixed costs and a higher
overhead rate.
(iii) Both factories may use different denominators in calculating the overhead
rates. For example, if factory Y uses normal capacity and factory X uses
maximum practical capacity then factory Y will have a higher overhead rate.
(iv) Current budgeted activity might be used by both firms to calculate the
overhead rate. The level of budgeted sales will determine budgeted activity.
The lower overhead rate of factory X might be due to a higher sales volume
rather than efficient factory operations.
(v) Different cost classification might result in different overhead rates. Factory
X might treat all expenditure as a direct cost wherever possible. For
example, employersโ costs might be charged out by means of an inflated
hourly wage rate. Factory Y may treat such items as overhead costs.
Solution IM 3.1
See answer to Question 3.22 in the text for the answer to this question.
Solution IM 3.2
(a) For the answer to this question see โBlanket overhead ratesโ in Chapter 3.
(b) For the answer to this question see Learning Note 3.1 on the open access website.
Solution IM 3.3
(a)
Solution IM 3.4
Production department
Service
department
Total
A
B
C
(ยฃ)
(ยฃ)
(ยฃ)
(ยฃ)
(ยฃ)
Direct
261 745
226 120
93 890
53 305
635 060
Indirect
135 400 (40%)
118 475 (35%)
67 700 (20%) 16 925 (5%) 338 500
Service dept
appointment
Allocation base (1)
COST ASSIGNMENT
1
23 410 ( )
โโโโโโโ 3
420 555
โโโโโโโ
17 760
=ยฃ23.68
per direct
labour hour
1
23 410 ( )
โโโโโโโ 3
368 005
โโโโโโโ
5 760
=ยฃ63.89
per m/c
hour
1
23 410 ( )
โโโโโโโ 3
185 000
โโโโโโโ
148 000
=ยฃ1.25
per hour
(70 230)
โโโโโโ
โ
โโโโโโ
โโโโโโโ
973 560
โโโโโโโ
5
Note:
1. Dept. A direct labour hours
= 10 ร 37 ร 48
= 17 760
Dept. B machine hours
= 5 ร 24 ร 48
=5760
Dept. C units
= 148 000
(b) Dept A
ยฃ
213.12
9 direct labour hours at ยฃ23.68
Dept B
3 m/c hours at ยฃ63.89
Dept C
100 units at ยฃ1.25
191.67
125.00
529.79
Cost per unit = ยฃ5.30 (ยฃ529.79/100)
Solution IM 3.5
Overhead analysis sheet
(a)
Production
Cutting
(ยฃ)
Tents
(ยฃ)
Bags
(ยฃ)
Stores
(ยฃ)
Canteen Maintenance
(ยฃ)
(ยฃ)
147 200
54 600
84 200
31 700
13 800
14 400
13 500
6 400
5 300
31 200
5 389
19 500
4 100
17 500
12 046
20 100
2 300
24 600
10 144
41 200
โ
2 500
951
15 000
18 700
3 400
2 536
45 000
24 200
5 000
634
11 120
13 900
9 730
2 085
3 475
1 390
359 400
59 409
67 046
66 874
46 736
43 111
76 224
โ
โ
โ
29 210
2 694
1 887
5 842
18 476
37 731
5 842
21 941
42 448
(46 736)
โ
(43 111)
5 842
โ
(82 066)
Reapportionment:
Storesc
Canteend
Maintenancee
Machine hours
Labour hours
359 400
87 000
112 000
โง
โจ
โฉ
Indirect wages
Consumable materials
Plant depreciation
Powera
Heat and lightb
Rent and ratesb
Building insuranceb
Service
Total
(ยฃ)
93 200 129 095 137 105
2 000 40 000 45 000
7 000 48 000 57 000
Machine hour rate
ยฃ46.60
ยฃ3.23
ยฃ3.05
Overheads per labour hour
ยฃ13.31
ยฃ2.69
ยฃ2.41
Notes
Bases of apportionment: a estimated power usage; b area; c value of issues; d direct
labour hours; e machine hours. Actual basis for other costs.
(b) See section on budgeted overhead rates in Chapter 3 for the answer to this
question. In addition the following points should be made:
(i) It draws attention to the under/over recovery of overheads arising from
changes in production levels.
(ii) There is difficulty in determining estimated overheads and an appropriate
level of activity when calculating predetermined overhead rates.
6
COST ASSIGNMENT
(a) Percentage of direct labour cost method = (ยฃ600 000/ยฃ200 000) 100
= 300% of direct labour cost
Direct labour hour method = (ยฃ600 000/40 000 direct labour hours)
= ยฃ15 per direct labour hour
Machine hour method
= (ยฃ600 000/50 000 machine hour)
= ยฃ12 per machine hour
Solution IM 3.6
(b) See โPredetermined overhead ratesโ in Chapter 3 for the answer to this question.
(c) The question states that the company has become machine-intensive and implies
that in the long term there is a closer association between overhead expenditure
and machine hours than the other two methods. Therefore the best measure of
overhead resources consumed by jobs or products is machine hours.
(d) Job Ax
Direct material
Direct labour
Direct expenses
(ยฃ)
3788
1100
422
Prime cost
Production overhead (120 machine hours ยฃ12)
5310
1440
Factory cost
Administrative overheads (20% ยฃ6750)
6750
1350
Total cost
Profit (ยฃ8100/0.90 ยฃ8100)
8100
900
Selling price
9000
Workings
Administration overhead absorption rate
= Total admin. overheads/total factory cost
= ยฃ328 000/ยฃ1 640 000
= 20% of factory cost
(e) The general characteristics of incentive schemes should ensure that:
(i) the scheme is simple to understand and administer;
(ii) payment should be made as quickly as possible after production;
(iii) there should be no limit on earnings and employees must be safe-guarded
from earning lower wages than time rate wages arising from problems which
are outside their control.
The advantages of incentive schemes are:
(i) increased production and lower average unit costs;
(ii) increased morale of the workforce;
(iii) attraction of more efficient workers to the company.
COST ASSIGNMENT
7
Solution IM 3.7
machine department overheads (ยฃ1 080 000)
(a) Predetermined machine hour rate =
machine hours (80 000)
Machining department = ยฃ13.50 per machine hour
Hand finishing department = ยฃ760 000/120 000 labour hours
= ยฃ6.33 per labour hour
(b) (i)
Machine department
Hand finishing department
(ยฃ)
(ยฃ)
Overhead incurred 84 500
67 100
Overhead absorbed 81 000 (6000 ยฃ13.50)
60 800 (9600 ยฃ6.33)
Under recovery of
overheads
3 500
6 300
(ii) Overheads that are apportioned to cost centres tend to be on an arbitrary basis
and are unlikely to be controllable by the cost centre manager. Managers should
be held accountable for only those overheads that they can control. See
โGuidelines for applying the controllability principleโ in Chapter 16 for a more
detailed discussion of controllable and non-controllable costs.
(c) Absorption costing is used by companies to ensure that all products/services bear
an equitable share of company overheads. Statement of Standard Accounting
Practice 9 (Replaced by Financial Reporting Standard 102) requires that stocks
should be valued at full production cost. Therefore absorption costing is
required to allocate overheads to products in order to meet financial
accounting requirements.
Solution IM 3.8
(a) In order to ascertain the actual overhead traced to the production departments, it
is necessary to allocate the service department overheads to the filling and sealing
departments:
Allocated
Reallocation of:
Canteen
Maintenance
Canteen
Maintenance
Filling
(ยฃ)
74 260
Sealing
(ยฃ)
38 115
14 625 (60%)
18 900 (70%)
486 (60%)
47 (70/97)
7 800 (32%)
1 950 (8%)
7 290 (27%) (27 000)
259 (32%)
65 (8%)
18 (27/97)
โ
108 318
53 482
Predetermined overhead rates:
Filling
(ยฃ)
Budgeted overheads
110 040
Budgeted direct
labour hours
13 100
Direct labour hour
overhead rate
8.40
Overhead incurred
Overhead allocated
ยฃ5.20)
(Under)/over recovery
8
Maintenance
(ยฃ)
25 050
Canteen
(ยฃ)
24 375
(24 375)
810 (3%)
(810)
โ
Sealing
(ยฃ)
53 300
10 250
5.20
108 318
53 482
107 688 (12 820 ยฃ8.40) 52 390 (10 075
(630)
(1 092)
COST ASSIGNMENT
(b) The objectives of overhead apportionment and absorption are:
(i) To meet the stock valuation and profit measurement requirements for
financial accounting purposes. Financial accounting regulations in most
countries require that all manufacturing overheads be traced to products for
stock valuation purposes.
(ii) For various decisions, such as pricing decisions, management require
estimates of the total product costs.
(iii) Overhead costs may be traced to different segments of the business, such as
product groups or geographical regions, in order to assess the performance
of each segment.
Overhead apportionment and absorption can be criticized on the following
grounds:
(i) The process includes many arbitrary apportionments and does not provide
an accurate indication of the resources consumed by each product. In tracing
overheads to products, the allocation procedure assumes that all overheads
are related to volume. This is inappropriate for many fixed overheads, since
they are fixed in the short term, and tend to be caused by factors other than
volume, such as the diversity of the product range, number of set-ups and
range of component parts which the firm stocks.
(ii) Fixed overheads are sunk costs, and will tend not to change in the short
term. Hence they are unaffected in the short term, irrespective of which
decisions are taken. Arbitrary overhead allocations should not be used for
decision-making purposes.
(iii) Overhead allocations are normally undertaken for stock valuation purposes.
The procedures are not intended to meet other requirements, such as
decision-making and performance evaluation.
(iv) Individuals should not be held accountable for costs which they cannot
control. Arbitrary apportionment of overheads is therefore inappropriate for
cost control and performance measurement purposes.
(a) (i) An over-absorption of overheads occurs because the actual overhead charged Solution IM 3.9
to products (or clients) exceeds the overheads incurred. Therefore ยฃ747 360
(ยฃ742 600 actual overheads + ยฃ4760 over-absorption were charged to clients
during direct hours worked, the actual professional staff hours worked during
the period were 99 648 (ยฃ747 360/ยฃ7.50 hourly overhead rate). Therefore
budgeted professional staff hours = 98 288 (99 648 1360).
(ii) Budgeted overhead expenditure
= Budgeted hours (98 288) ร Overhead rate (ยฃ7.50)
= ยฃ737 160
(b) To determine the overhead rate the senior staff hours should be weighted by a
factor of 1.4 and the junior staff hours by a factor of 1.0:
Senior staff= 21 600 ร 1.4 = 30 240
Junior staff= 79 300 ร 1.0 = 79 300
109 540
Allocation of overheads:
Senior staff= 30 240/109 540 ร ยฃ784 000 = ยฃ216 434
Junior staff= 79 300/109 540 ร ยฃ784 000 = ยฃ567 566
ยฃ784 000
COST ASSIGNMENT
9
Senior staff overhead allocation rate = ยฃ216 434/21 600
= ยฃ10.020 per hour
Junior staff overhead allocation rate = ยฃ567 566/79 300 hours
= ยฃ7.157 per hour
(c) Presumably the senior staff consume a greater proportion of the overhead costs
than the junior staff and the revised method is an attempt to reflect this difference
in resource consumption. For example, senior staff are likely to require more
office space and make greater demands on secretarial time, telephones, etc. The
revised method creates two separate cost centres and overhead rates whereas the
previous method used a single blanket rate for the whole organization.
(d) See the section on under- and over-recovery of overheads in Chapter 3 for the
answer to this question. Differences between overhead incurred and overhead
absorbed may be due to:
(1) differences between actual and budgeted expenditure;
(2) differences between actual and budgeted activity level.
Solution IM 3.10
(i) With the step-wise method the costs of the first service department (Department G
specified in the question) are reapportioned to the second department but return
allocations are not made from the second department back to the first department.
Production depts
Internal services
1
2
G
H
(ยฃ000)
(ยฃ000)
(ยฃ000)
(ยฃ000)
Overheads
870
690
Costs
160
82
G apportioned
96 (60%)
48 (30%)
160
16 (10%)
โโโโ
โโโโ
98
H apportioned
61 (50/80)
37 (30/80)
98
โโโโ
โโโโ
โโโโ
1027
775
โโโโ
โโโโ
(ii) Let G = Service Department G overheads
Let H = Service Department H overheads
G = 160 + 0.2H
H = 82 + 0.1G
Rearranging the above equations
0.2H + G = 160
1H 0.1 G = 82
(1)
(2)
Multiply equation (1) by 1 and equation (2) by 10
0.2H + G = 160
10H G = 820
Add the above equations together:
9.8H = 980
H = 100
Substituting for the value of H in equation (1)
0.2 (100) + G = 160
G = 180
10
COST ASSIGNMENT
Internal
Services
G (180 ร 90%)
H (100 ร 80%)
Total
(ยฃ000)
162
80
โโโ
242
Overheads (given)
Production depts
1
(ยฃ000)
(69)
108
(39)
5
(8)
50
(38)
โโโโ
158
870
โโโโ
1028
โโโโ
2
(ยฃ000)
54
30
โโโ
84
690
โโโ
774
โโโ
(iii) The simultaneous equation method will yield more accurate allocations because it
takes into account the fact that service departments serve each other whereas the
step-wise method ignores such reciprocal usage. The step-wise method involves
simpler computations and, in this question, does not give a significantly different
answer. However, the step-wise method may yield inaccurate results where
service costs are high and there are more than two service departments with
significantly different usage ratios between the departments.
(a)
Primary allocation
Apportionment of
general factory
overhead a
Charges by service
cost centre 1 b
Charges by service
cost centre 2 c
Budgeted direct
labour hours
Absorption rates
General
factory
overhead
(ยฃ)
210 000
(210 000)
โโโโโโโ
โ
โโโโโโโ
โโโโโโโ
Overhead analysis
(ignoring reciprocal allocations)
Service cost
Production cost
centres
centres
1
2
A
B
(ยฃ)
(ยฃ)
(ยฃ)
(ยฃ)
93 800
38 600
182 800
124 800
10 500
โโโโโโโ
104 300
21 000
โโโโโโ
59 600
31 500
โโโโโโโโ
214 300
147 000
โโโโโโโโ
271 800
(104 300)
โโโโโโโ
โ
โโโโโโโ
โโโโโโโ
โ
โโโโโโ
59 600
91 262
โโโโโโโโ
305 562
13 038
โโโโโโโโ
284 838
(59 600)
โโโโโโ
โ
โโโโโโ
โโโโโโ
8 221
โโโโโโโโ
ยฃ313 783
โโโโโโโโ
โโโโโโโโ
51 379
โโโโโโโโ
ยฃ336 217
โโโโโโโโ
โโโโโโโโ
120 000
โโโโโโโโ
โโโโโโโโ
ยฃ2.61
โโโโโโโโ
โโโโโโโโ
20 000
โโโโโโโโ
โโโโโโโโ
ยฃ16.81
โโโโโโโโ
โโโโโโโโ
Solution IM 3.11
Notes
a General factory overhead is apportioned to service cost centres before reallocation
to production centres as indicated in note (i) of the question.
b Because reciprocal allocations are not made, the costs allocated to service cost centre 1 are reallocated as follows:
ยฃ91 262 (63/72 ยฃ104 300) to production cost centre A
ยฃ13 038 (9/72 ยฃ104 300) to production cost centre B
c Reciprocal charges are not made. Therefore the allocation is as follows:
4 000/29 000 ยฃ59 600 = ยฃ8 221 to production cost centre A
25 000/29 000 ยฃ59 600 = ยฃ51 379 to production cost centre B
COST ASSIGNMENT
11
(b) The difference may be due to the following:
(i) Changes occurred in projected overhead expenditure compared with
expenditure which was used to determine the current yearโs overhead rate.
(ii) Current overhead rates do not include a proportion of the service cost
centres overhead.
(iii) Budgeted activity for the next year is greater than the current year for
production cost centre A. If this is not matched by a corresponding increase
in overhead expenditure then the hourly overhead rate will decline.
Budgeted activity for production cost centre B is lower than the current year,
resulting in an increase in the overhead rate. Because fixed overheads do not
change in relation to activity, the hourly overhead rate will fluctuate
whenever changes in activity occur. (See Example 3.2 in Chapter 3 for an
illustration.)
(c) This question can be answered by using either the repeated distribution or
simultaneous equation methods. Both methods are illustrated in Appendix 3.1 to
Chapter 3. The simultaneous equation method is illustrated below:
Let
X = total overhead of service cost centre 1
Y = total overhead of service cost centre 2
Then
X = 104 300 + 310Y (i.e. 1000/30 000 hrs of service cost centre 2 overheads)
Y = 59 600 + 15X (i.e. 18% out of total of 90% of service cost centre 1 overheads)
Rearranging the above equations:
X 310Y = 104 300
15X + Y = 59 600
(1)
(2)
Multiply equation (1) by 1 and equation (2) by 5:
X 310Y = 104 300
X + 5Y = 298 000
Adding the above equations together:
149
Y = 402 300
30
402 300 30
Y=
149
Y = 81 000
Substituting for Y in equation (1) results in the following equation:
X 310 81 000 = 104 300
X = 107 000
The service cost centre overheads of ยฃ107 000 (service cost centre 1) and ยฃ81 000
(service cost centre 2) are now apportioned to the production cost centres as follows:
12
COST ASSIGNMENT
Primary allocation
Apportionment of
general factory
overhead
Charges by service
cost centre 1 a
Charges by service
cost centre 2 b
Budgeted direct
labour hours
Absorption rates
General
factory
overhead
(ยฃ)
210 000
Service cost
centre
1
2
(ยฃ)
(ยฃ)
93 800
38 600
Production cost
centre
A
B
(ยฃ)
(ยฃ)
182 800
124 800
(210 000)
โโโโโโโโ
โ
โโโโโโโโ
โโโโโโโโ
10 500
โโโโโโ
104 300
21 000
โโโโโโ
59 600
31 500
โโโโโโโ
214 300
147 000
โโโโโโโ
271 800
(107 000)
21 400
74 900
10 700
2 700
โโโโโโ
โ
โโโโโโ
โโโโโโ
(81 000) 10 800
โโโโโโ
โโโโโโโ
โ
ยฃ300 000
โโโโโโ
โโโโโโโ
โโโโโโ
โโโโโโโ
67 500
โโโโโโโ
ยฃ350 000
โโโโโโโ
โโโโโโโ
120 000
โโโโโโ
โโโโโโ
ยฃ2.50
โโโโโโ
โโโโโโ
20 000
โโโโโโ
โโโโโโ
ยฃ17.50
โโโโโโ
โโโโโโ
Notes
a 18/90 ยฃ107 000 = ยฃ21 400 to service cost centre 2 (18% out of 90%)
63/90 ยฃ107 000 = ยฃ74 900 to production cost centre A
9/90 ยฃ107 000 = ยฃ10 700 to production cost centre B
b 1000/30 000 ยฃ81 000 = ยฃ2700 to service cost centre 1
4000/30 000 ยฃ81 000 = ยฃ10 800 to production cost centre A
25 000/30 000 ยฃ81 000 = ยฃ67 500 to production cost centre B
(d) The answer should include the following points:
(i) The overhead rate calculations do not distinguish between fixed and variable
elements. Such an analysis is necessary for decision-making purposes.
(ii) The majority of service cost centre 1 costs are variable. It is preferable to
determine an activity measure which exerts most influence on the variable
costs and apportion the costs on the basis of this measure. The present
method of apportionment appears to be inappropriate.
(iii) Service cost centre 2 is the maintenance department and the majority of costs
are fixed, thus suggesting preventive maintenance be undertaken. The
question does not make it clear which hourly base is used for allocating
overheads (direct labour hours or machine hours). Machine hours should be
used for allocating variable costs, since these costs are likely to vary with this
activity base. Preventive maintenance should be apportioned on the basis of
the planned hours which the maintenance staff intend to allocate to each
department.
(iv) Production cost centre B is highly mechanized, thus suggesting that a
machine hour rate might be preferable to the present direct labour hour rate.
COST ASSIGNMENT
13
Solution IM 3.12
Department cost statement
(a)
Direct variable costs:
Materials
Labour
Factory-wide
indirect cost
per floorspace
Service departments
Administration a
Maintenance b
Warehousing b
Cost per unit:
Belts
(ยฃ000)
Braces Administration
(ยฃ000)
(ยฃ000)
Maintenance
(ยฃ000)
Warehousing
(ยฃ000)
Total
(ยฃ000)
120
80
โโโโ
200
130
70
โโโโ
200
โ
50)
โโโโ
50)
20)
80)
โโโโ
100)
30)
20)
โโโโ
50)
300
300
โโโโโ
600
400
โโโโ
600
400
โโโโ
600
50)
โโโโ
100)
100)
โโโโ
200)
50)
โโโโ
100)
1000
โโโโโ
1600
40
โโโโ
640
79
108
โโโโ
ยฃ827
โโโโ
40
โโโโ
640
79
54
โโโโ
ยฃ773
โโโโ
(100)
โโโโ
โ
โ
โ
โโโโ
โ
โโโโ
10)
โโโโ
210)
(264)
54)
โโโโ
โ
โโโโ
10)
โโโโ
110)
106)
(216)
โโโโ
โ
โโโโ
โ
โโโโโ
1600
โ
โ
โโโโโ
ยฃ1600
โโโโโ
ยฃ827 000
Belts
100 000
Braces
ยฃ773 000
50 000
= ยฃ8.27
= ยฃ15.46
Notes
a Administration does not receive any charges from the other service departments.
Therefore the reciprocal basis does not apply.
b The simultaneous equation method is used to allocate the maintenance and warehouse costs.
Let
M = total cost of the maintenance department
W = total cost of the warehousing department
Then
M = 210 + 0.25W
W = 110+ 0.4M
(1)
(2)
Multiplying equation (1) by 4 and equation (2) by 1, and rearranging the resulting equations:
4M W = 840
0.4M + W = 110
3.6M
M
= 950
= ยฃ263.89
Substituting the value of M into equation (2):
W = 110 + 0.4 263.89
W = ยฃ215.56
(b) Kaminsky Ltd has spare capacity, and therefore any sales revenue in excess of
variable costs will provide a contribution towards fixed costs and profit.
Therefore it is necessary to calculate the variable cost per unit for belts and braces.
The calculations of the unit variable cost are as follows:
14
COST ASSIGNMENT
Direct variable costs:
Materials
Labour
Service departments
Administration
Maintenance a
Warehousing a
Belts
(ยฃ000)
Braces Administration
(ยฃ000)
(ยฃ000)
120
80
โโโโ
200
130
70
โโโโ
200
20
โโโโ
220
39.6
53.9
โโโโ
313.5
โโโโ
20
โโโโ
220
39.6
26.9
โโโโ
286.5
โโโโ
Variable cost per unit:
Belts
Maintenance
(ยฃ000)
Warehousing
(ยฃ000)
Total
(ยฃ000)
โ))
50)
โโโ
50)
20)
80)
โโโโโ
100)
30)
20)
โโโโ
50)
300
300
โโโ
600
(50)
โโโ
โ))
โ))
โ))
โโโ
โ))
โโโ
5)
โโโโโ
105)
(132)
26.95)
โโโโโ
โ)
โโโโโ
5)
โโโโ
55)
52.8)
(107.8)
โโโโ
โ)
โโโโ
โ
โโโ
600
โ
โ
โโโ
600
โโโ
ยฃ313 500
100 000
Braces
ยฃ286 500
50 000
= ยฃ3.135
= ยฃ5.73
Note
a The simultaneous equation method is used to allocate the service department costs
as follows:
Let
M = maintenance department variable costs
W = warehousing department variable costs
Then
M = 105 + 0.25W
W = 55 + 0.4M
(1)
(2)
Multiplying equation (1) by 4 and equation (2) by 1:
4M W = 420
0.4M + W = 55
3.6M
= 475
M
= 131.94
Substituting in equation (2):
W = 55 + 0.4 131.94
W = 107.8
Camfan order
Contract price
Variable costs (1000 belts at ยฃ3.135)
(ยฃ)
5000
3135
Contribution
1865
If this order is accepted, profits will increase by ยฃ1865, provided that better
opportunities are not available and the normal selling price will not be affected. It
is unlikely that such a small order will affect the normal selling price.
Mixon Spenders contract
The normal unit cost based on a normal activity of 100 000 belts is ยฃ8.27. If this
unit cost is used as the basis for determining the โcost-plusโ selling price then the
agreed selling price will be ยฃ9.10 (ยฃ8.27 + 10%). The normal selling price will
be ยฃ9.92 (ยฃ8.27 + 20%). The contribution from supplying 100 000 belts will
be ยฃ596 500 [(ยฃ9.10 ยฃ3.135 variable cost) 100 000]. Total demand will now
be 200 000 belts, but maximum output is 150 000 belts. Therefore existing sales
will be reduced by 50 000 belts. The lost contribution is ยฃ339 250 [50 000
(ยฃ9.92 ยฃ3.135)]. Consequently total contribution will increase by ยฃ257 250.
COST ASSIGNMENT
15
Alternatively, Kaminsky might base selling price on unit costs at maximum
capacity of 150 000 units. The revised unit cost will be as follows:
Fixed costs apportioned to belts = ยฃ513 500 (ยฃ827 000 total cost ยฃ313 500
variable cost)
Fixed costs per unit (ยฃ)
= 3.42 (ยฃ513 500/150 000 units)
Variable cost per unit (ยฃ)
= 3.135
โโโโ
Total cost per unit (ยฃ)
= 6.555
โโโโ
Selling price for contract
= ยฃ7.21 (ยฃ6.555 + 10%).
The total contribution from the contract will be ยฃ407 500, consisting of 100 000
units at a contribution per unit of ยฃ4.075 (ยฃ7.21 ยฃ3.135). This will still cover
the contribution sacrificed on existing business. On the basis of the above
quantitative information, the contract should be accepted. However, before
acceptance, the following qualitative factors should be considered:
(i) Will the long-term disadvantages from a loss of customer goodwill from
depriving normal customers of 50 000 units outweigh the short-term advantage of taking on the contract?
(ii) An attractive feature of the contract is that it will result in certain sales of
2000 units per week, thus enabling production, cash flows etc. to be forecasted more accurately.
(c) For the answer to this question see โalternative denominator level measuresโ in
Chapter 7. In addition the answer should emphasize that normal overhead rates
reflect a long-term planned activity base which is expected to satisfy demand
levels over a series of years. Over this period, fluctuations in customer demand,
seasonal and cyclical changes will be incorporated into an annual rate. A
normalized overhead rate recognizes that the companyโs overhead cost
commitment is related to the long-run demand for its products. A normalized
overhead rate is preferable for pricing purposes, since the alternative of basing
overhead rates on the activity for next year will result in higher selling prices
when demand is low if cost-plus pricing is used. Prices should be lower when
demand is depressed. A normalized overhead rate should avoid such
inconsistencies.
16
COST ASSIGNMENT
Document Preview (12 of 378 Pages)
User generated content is uploaded by users for the purposes of learning and should be used following SchloarOn's honor code & terms of service.
You are viewing preview pages of the document. Purchase to get full access instantly.
-37%
Management and Cost Accounting, 10th Edition Solution Manual
$18.99 $29.99Save:$11.00(37%)
24/7 Live Chat
Instant Download
100% Confidential
Store
William Taylor
0 (0 Reviews)
Best Selling
The World Of Customer Service, 3rd Edition Test Bank
$18.99 $29.99Save:$11.00(37%)
Chemistry: Principles And Reactions, 7th Edition Test Bank
$18.99 $29.99Save:$11.00(37%)
Test Bank for Hospitality Facilities Management and Design, 4th Edition
$18.99 $29.99Save:$11.00(37%)
Solution Manual for Designing the User Interface: Strategies for Effective Human-Computer Interaction, 6th Edition
$18.99 $29.99Save:$11.00(37%)
Data Structures and Other Objects Using C++ 4th Edition Solution Manual
$18.99 $29.99Save:$11.00(37%)
2023-2024 ATI Pediatrics Proctored Exam with Answers (139 Solved Questions)
$18.99 $29.99Save:$11.00(37%)