Construction Estimating Using Excel, 3rd Edition Solution Manual
Preview Extract
CHAPTER 2: OVERVIEW OF THE ESTIMATING AND BIDDING PROCESS
LEARNING OBJECTIVES
At the completion of this chapter the student should be able to:
โข Describe the steps taken to complete an estimate.
โข Identify the general scope of work and the items which need to be bid to complete an estimate.
โข Identify how information flow between the spreadsheets used in this book.
INSTRUCTIONAL HINTS
โข
During the lecture show how the different topics shown in Figure 2-1 relate to the chapters in
the textbook. This will help them understand the organization of the course. The relationships
are as follows:
o Request subcontractor quotes: Chapter 24
o Quantity takeoff: Chapters 4 โ 18
o Materials pricing: Chapter 19
o Labor pricing: Chapters 20, 21, and 23
o Equipment pricing: Chapter 22 and 23
o Prepare bid documents: Chapter 28
o Add markups: Chapter 25
o Combine pricing: Chapter 26
o Review bids for errors: Chapter 27
o Submit the bid: Chapter 28
o Project buyout: Chapter 29
ACTIVITIES
โข
Provide the students with copies of the Summary worksheet shown in Figure 2-2 and have
them identify the items on the Summary worksheet which need to be bid to complete the bid
for the Johnson Residence, the West Street Video, or another set of plans. Appendix B in
Construction Estimating using Excel contains a list of items included in each of the cost codes on
the Summary worksheet and should be used if a student is not sure where construction
materials are located on the Summary worksheet.
INSTRUCTIONAL RESOURCES
โข
โข
โข
โข
PowerPoint slide show: PowerPoint LecturesChapter 02.ppt from the IM Resource Files
Summary worksheet: The Summary tab of Excel ExercisesChapter 32.xls from the IM Resource
Files
Quantity takeoff for the Johnson Residence: Johnson Residence Estimate.xls
Quantity takeoff for the West Street Video: West Street Video Estimate.xls
SOLUTIONS TO THE TEXTBOOK PROBLEMS
Get additional help, eliminate some of the estimating steps, or decide not to bid on the project.
Construction Estimating using Excel
Chapter 2
It gives the surety time to prepare the bid bond, obtain the necessary signatures on the bond, and mail it
to the contractor; thus eliminating the need to make a special trip to the suretyโs office to pick up the
bond.
The subcontractor will need to find a time to come in, look at the plans and specifications, and prepare
their estimate. When dealing with a limited number of plan sets, it can be quite a challenge to give all of
the subcontractors a chance to look at the plans within the allowed time for the bid.
To ensure you have a bid for each category of work, rather than having multiple bids in one category
and no bids in another category.
They carry the most risk should the contractor have to bid these items themselves.
Vendors often do not guarantee their quantities are accurate, and the estimator should prepare their
own quantity survey to make sure there are sufficient quantities of materials to complete the work.
Mark blanks with Post-itsยฎ.
To avoid missing items or having items included in the bid twice (for example, two subcontractors on the
project have an item included in their bids).
Completeness of the scope of work, price, and past experience with the subcontractor.
Subcontractor or vendor contact information, project name, what they are bidding, any specific
exclusions, if freight and sales tax are included, bid price, the date and time the bid was received, and
who took the bid.
To avoid forgetting to get some of the necessary information.
Profit markup, overhead markup, building permit costs, bonding costs, and sales tax.
Companyโs overhead costs. The project specific overhead should be bid as part of the project costs.
The process of hiring subcontractors and procuring materials and equipment for the construction
project.
During project buyout and the close-out audit.
The answers are as follows:
32-130 Rebar. Sidewalks and all exterior concrete should be included under Division 32
22-100 Plumbing. Bathroom sinks are a plumbing fixture. They should not be listed as a toilet
and bath accessory, which is for towel bars, etc.
07-400 Siding.
05-500 Metal Fabrications.
06-210 Wood Trim.
33-100 Waterline.
The following job cost codes will be needed:
03200 Rebar
03300 Footings and Foundation–Labor
03310 Footings and Foundation–Concrete
03320 Slab/Floor–Labor
03330 Slab/Floor–Concrete
04200 Masonry
06100 Rough Carpentry
06110 Lumber
06120 Trusses
06210 Wood Trim
06400 Cabinetry and Countertops
07200 Insulation
07220 Stucco
07400 Siding
07500 Roofing
07710 Rain Gutters
08100 Metal Doors
08110 Wood Doors
08300 Overhead Doors
08500 Windows
08700 Hardware
09200 Drywall
09300 Ceramic Tile
09600 Flooring
09900 Paint
10210 Toilet & Bath Accessories
22000 Plumbing
23000 HVAC
26000 Electrical
31200 Grading and Excavation
32110 Site Concrete-Labor
32120 Site Concrete-Concrete
33100 Water Line
33300 Sewer Line
The items in the schedule and their due dates should be based on the items that required by the
instructor as part of the coursework and their associated due dates.
The following job cost codes will be needed:
02400 Demolition
03200 Rebar
03300 Footings and Foundation–Labor
03310 Footings and Foundation–Concrete
03320 Slab/Floor–Labor
03330 Slab/Floor–Concrete
04200 Masonry
05100 Structural Steel
05200 Joist and Deck
05900 Erection
06100 Rough Carpentry
06110 Lumber
06400 Cabinetry and Counter Tops
07200 Insulation
07500 Roofing
07600 Sheet Metal
07700 Roof Specialties
08100 Metal Doors and Frames
08400 Store Fronts
08700 Hardware
09200 Drywall
09300 Ceramic Tile
09500 Acoustical Ceilings
09600 Flooring
09900 Paint
10210 Toilet and Bath Accessories
10400 Fire Extinguishers and Cabinets
21000 Fire Sprinklers
22000 Plumbing
23000 HVAC
26000 Electrical
31200 Grading and Excavation
32100 Asphalt
32110 Site Concrete-Labor
32120 Site Concrete-Concrete
32130 Rebar
32900 Landscaping
33100 Water Line
33300 Sanitary Sewer
33400 Storm Drain
Construction Estimating using Excel
Chapter 2
The items in the schedule and their due dates should be based on the items that required by the
instructor as part of the coursework and their associated due dates.
Document Preview (4 of 412 Pages)
User generated content is uploaded by users for the purposes of learning and should be used following SchloarOn's honor code & terms of service.
You are viewing preview pages of the document. Purchase to get full access instantly.
-37%
Construction Estimating Using Excel, 3rd Edition Solution Manual
$18.99 $29.99Save:$11.00(37%)
24/7 Live Chat
Instant Download
100% Confidential
Store
Evelyn Miller
0 (0 Reviews)
Best Selling
The World Of Customer Service, 3rd Edition Test Bank
$18.99 $29.99Save:$11.00(37%)
Chemistry: Principles And Reactions, 7th Edition Test Bank
$18.99 $29.99Save:$11.00(37%)
Test Bank for Hospitality Facilities Management and Design, 4th Edition
$18.99 $29.99Save:$11.00(37%)
Solution Manual for Designing the User Interface: Strategies for Effective Human-Computer Interaction, 6th Edition
$18.99 $29.99Save:$11.00(37%)
Data Structures and Other Objects Using C++ 4th Edition Solution Manual
$18.99 $29.99Save:$11.00(37%)
2023-2024 ATI Pediatrics Proctored Exam with Answers (139 Solved Questions)
$18.99 $29.99Save:$11.00(37%)